Super Nyadi Hydro power Project is located
at Lamjung District in Western Development Region of Nepal being developed by
Siuri Nyadi Power Pvt. Ltd. It is a run-off-river (ROR) with installed capacity
of 42.27 MW with the net head of 685.51m and design discharge of 7.34 m3/s at
Q40 including the additional discharge from two tributaries.
Main Components:
Headworks, gravel trap, surface
desander,drop intakes (2nos ) Headrace tunnel (6.904 Km), adits, surgetank,
drop shaft, underground powerhouse, tailrace tunnel, access tunnel, 132kV
transmission line
Major Jobs:
Ø
DPR
Ø
Feasibility
Report for Project (Capacity Upgrade from 40MW to 42.27MW)
Ø
Feasibility
Report of Transmission line
Ø
Power
upgrade from 40MW to 42.27MW